Dry lining is the fixing of plasterboard to the inside of walls and ceilings, on adhesive dabs or a timber or metal frame, to give a flat surface ready for decoration. JMC Drywall Ltd, a dry lining contractor in Tiptree, Essex, explains the methods and finishes used on new-build homes. Dry lining runs on every current scheme we name.

By JMC Drywall Ltd. Last updated .

What is dry lining

Dry lining is a way of forming the inside faces of a building from plasterboard instead of wet plaster. The board is bonded to masonry with adhesive, screwed to a metal or timber frame, or fixed to studs and joists. The joints are then filled and taped, or the face skimmed, ready for decoration.

The UK code of practice is BS 8000-8:2023, Workmanship on construction sites. Design and installation of dry lining systems. BSI lists it as current. It covers dry lining with gypsum-based plasterboards in dwellings and other buildings, and it replaced BS 8212:1995 and BS 8000-8:1994.

The standard treats the lining as part of how the building performs. Its scope names separation, fire protection, stability, applied loadings, acoustics, thermal insulation and aesthetics.

Why is it called dry lining, and how is it different from plastering

It is called dry lining because the board is made in a factory and fixed dry, so very little water goes into the building. CITB's Go Construct gives the same reason: dry lining needs less water than plastering. Wet plaster is mixed on site, trowelled on in coats and left to dry.

That difference shows in the programme. A plastered wall holds water that has to dry out before decoration. Siniat says its direct bond lining reduces drying out time and speeds up internal fit-out. On a dry lined wall the wet materials are the adhesive behind the board and the compound or skim on its face.

The two trades still meet. A skim coat over plasterboard is a wet finish on a dry lined wall. Go Construct also notes that plaster can form mouldings such as cornices and ceiling roses, which board cannot.

Dry lining methods: dot and dab, metal furring and stud walls

There are four main ways to hold the board. It can be bonded to masonry on dabs of adhesive, known as dot and dab or direct bond. It can be screwed to metal channels fixed to the wall, or to a free-standing metal frame. On stud walls it is screwed to both faces of timber or metal studs.

Siniat's direct bond system sets dabs of bonding compound 250mm long and 50 to 75mm wide, at 600mm maximum horizontal and 300mm maximum vertical centres, with at least three columns a board. A continuous ribbon runs 50mm from the head and base of each board and around the wall perimeter for air-tightness. Knauf asks for a continuous band at floor and ceiling line to stop air leakage.

Direct bond suits level, sound masonry. Siniat rules out bonding to external solid walls and basements, and asks for a mechanical fix where moisture can reach the wall. Its lining on brackets and furring channel allows a cavity of up to 130mm. Its independent wall lining stands clear of the wall on its own studs.

Dry lining methods compared. Cavity figures from the Siniat Drywall Manual, Linings, version 3.0.0, November 2024
MethodHow the board is heldCavity behind the boardWhere it suits
Direct bond, or dot and dabAdhesive dabs on masonryService cavity of 10 to 25mmLevel blockwork or brickwork in normal humidity
Shallow wall channelMetal channels bonded or fixed to the wallIntermittent cavity up to 25mmWalls where the board cannot be bonded direct, such as some concrete
Metal frame lining on bracketsFurring channel held off the wall on adjustable bracketsUp to 130mmStable walls needing room for services, insulation or more correction
Independent wall liningFree-standing metal studs, clear of the wallAny depthWalls unsuitable for a direct fixing, or open to moisture
Stud partitionScrewed to both faces of timber or metal studsThe depth of the studInternal walls between rooms

Drywall and plasterboard: are they the same thing

Yes, in practice. Drywall is the North American name for gypsum board and for the trade that fixes it. In the UK the board is called plasterboard and the trade dry lining. Manufacturers here use both words. Siniat, for one, publishes its technical guidance as the Siniat Drywall Manual.

Plasterboard is a gypsum core faced with paper. Its product standard is BS EN 520, Gypsum plasterboards. Definitions, requirements and test methods. It covers boards made to take direct decoration and boards made to take gypsum plaster.

Most new homes use more than one board, picked room by room in the specification. Moisture resistant board goes where there is steam, fire board on a fire line, denser board where sound matters and insulated board on outside walls. Our guide to plasterboard fire ratings explains why the minutes belong to the whole wall.

Tape and jointing or a skim: how dry lining is finished

A dry lined wall is finished in one of two ways. Tape and jointing fills and tapes the joints between boards and spots the screw heads, leaving the board face to take paint. A skim coat is a thin layer of plaster trowelled over the whole face. The specification decides which.

The board edge follows the finish. A tapered edge leaves a shallow recess along each long side for tape and compound. A square edge suits a skim that covers everything.

Siniat states its lining performance for imperforate, jointed systems. So a joint left open is a gap in the tested system as well as a mark under the paint.

Where dry lining comes in the build of a new home

Dry lining follows first fix and comes before second fix. The plot has to be weathertight, with windows and external doors in, and the first fix electrics, plumbing and ventilation carcassed. The boarders then close the walls and ceilings, and the second fix trades and decorators follow.

NHBC's best practice guide calls first fix the skeleton of the home before boarding and painting. It asks for windows and doors to give a watertight shell before other first fix work starts. Its judges mark dry lining on screw spacing, cuts around sockets and solid dabbing of boards.

Once a wall is boarded, what sits behind it is hidden. A back box, cable or pipe found missing afterwards means cutting the new board open and making good.

Who does dry lining: fixers, tapers and jointers

Dry lining is two jobs. Fixers, also called dry liners or boarders, measure, cut and fix the board. Tapers and jointers, sometimes called finishers, fill and tape the joints and sand them ready for paint. CITB's Go Construct describes the role in the same two parts, fixing and finishing.

Go Construct lists routes into the trade through college or an apprenticeship. The main apprenticeship it names is Interior Systems Installer, equivalent to NVQ Level 2 and lasting 24 months.

On a housing site the two are often let as one package. On JMC Drywall schemes the fixers and tapers answer to one named contracts manager, and each plot is photographed and signed off before it is offered to the client.

Questions

What buyers ask us

Is dry lining better than plastering for a new-build home?
Each has a place, and the specification decides. JMC Drywall Ltd carries out both on new-build housing. Dry lining puts far less water into the plot, so decoration can start sooner, and the cavity behind the board takes services and insulation. A skim over plasterboard gives one even, harder surface. Traditional wet plaster on masonry takes longest to dry.
Can plasterboard be dot and dabbed onto any wall?
No. Direct bonding suits level, clean masonry such as blockwork and brickwork. Siniat's guidance rules out external solid walls and basements, and asks for a mechanical fix where moisture can reach the wall. Very low suction backgrounds may need mechanical fixing, and high suction ones a PVAC bonding agent. Knauf says its adhesive should not be used for vapour check boards.
What is the British Standard for dry lining?
BS 8000-8:2023, Workmanship on construction sites. Design and installation of dry lining systems. Code of practice. BSI lists it as current. It gives recommendations for the design and installation of dry lining with gypsum-based plasterboards, including workmanship and finishing, and it replaced BS 8212:1995. It does not cover dry lining to light gauge steel framing.
How much space does dry lining take from a room?
It depends on the method. With direct bond, Siniat gives a service cavity of 10 to 25mm behind the board, plus the board itself. Go Construct names 9.5mm and 12.5mm as the two standard board thicknesses. A lining on metal brackets can stand up to 130mm off the wall, and an independent lining can be any depth.
Does a dry lined wall need a skim coat?
No. Tape and jointing gives a surface ready for paint without a skim, and BS EN 520 covers boards made for direct decoration as well as boards made to take plaster. A skim is a choice in the specification, usually for a harder, even surface. The two finishes suit different board edges, so the choice is made before the board is ordered.

Tender enquiries

Pricing your next scheme?

Send us the drawings, specification, inclusions list, scope and programme. You will get a fully compliant price by your tender deadline, and a straight answer on whether we have the labour to meet your programme.

Email the estimating team
estimating@jmcdrywallltd.co.uk

We reply the same week.